NMED claims revised Consent Order is a stronger enforcement tool. Not so!

Rebecca Moss at the New Mexican has another hard charging article on safety lapses at the Los Alamos Lab.  See “Lab might have known dangerous waste was unmarked” at www.santafenewmexican.com/news/local_news/lab-might-have-known-dangerous-waste-was-unmarked/article_19d37b31-219a-5620-954c-a62fa9620d2a.html

If the New Mexico Environment Department is claiming, as this article reports, that its revised Consent Order governing cleanup at the Los Alamos National Laboratory (LANL) is a stronger enforcement tool than the original 2005 Consent Order, then it is being highly disingenuous (to put it politely).

Interested citizens should judge for themselves. The 2016 revised Consent Order is available at https://web.archive.org/web/20170615022416/http://www.lanl.gov/environment/protection/compliance/order-on-consent.php

The revised Consent Order was a giveaway by NMED to the Department of Energy and the Lab, surrendering the strong enforceability of the old Consent Order. It is clearly the opposite of the old Consent Order, whose underlying intent was to make DOE and LANL get more money from Congress for accelerated cleanup.

The new Consent Order allows LANL and DOE to get out of future cleanup by simply claiming that it’s too expensive or impractical to clean up. Not long after the revised Consent Order went into effect, DOE took advantage by estimating a lifetime budget that projected a top range of $3.8 billion to clean up the Lab by 2040. That works out to only around $150 million per year, when NMED is already on record that $250 million per year is needed. Most egregious of all, DOE claimed that only 5,000 cubic meters of wastes needed to be cleaned up, purposively misleading the public and politicians by willfully ignoring the ~200,000 cubic meters of radioactive and toxic wastes known to be buried in LANL’s biggest dump alone.

Some of the highlights (or perhaps better put as lowlights) of the revised Consent Order are:

  • “The Parties agree that DOE’s project’s plans and tools will be used to identify proposed milestones and targets.” P. 28. “DOE shall define the use of screening levels and cleanup levels at a site…” P. 32. This puts the Department of Energy in the driver’s seat, not the New Mexico Environment Department
  • “DOE shall update the milestones and targets in Appendix B on an annual basis, accounting for such factors as… changes in anticipated funding levels.” P. 29. Therefore the new Consent Order is held hostage to DOE’s budget.“… [DOE and NMED] shall meet to discuss the appropriation and any necessary revision to the forecast, e.g. DOE did not receive adequate appropriations from Congress…” P. 30. Again, the new Consent Order and therefore cleanup at LANL will be held hostage to DOE funding, when DOE’s own track record makes clear that its priority is expanded nuclear weapons production paid for in part by cutting cleanup and nonproliferation programs.
  • “If attainment of established cleanup objectives is demonstrated to be technically infeasible, DOE may perform risk-based alternative cleanup objectives…” P. 34. DOE can opt out because of “impracticability” or cost of cleanup. P. 35. This creates giant loopholes that threaten comprehensive cleanup at LANL.

Given all this, how can NMED claim with a straight face that the 2016 revised Consent Order is a stronger enforcement tool? This is just more of the Martinez administration coddling the nuclear weapons industry in New Mexico. Indeed, NMED had the gall to give LANL more than 150 extensions to the original Consent Order, and then turned around and claimed the Consent Order was not working and replaced it with a toothless tiger. Furthermore, and this is telling, the main Consent Order negotiator for NMED left shortly after it was signed to go work for a DOE contractor!

New Mexicans should demand comprehensive, enforceable cleanup at the Lab, which would be a real win-win, permanently protecting our precious water resources while providing hundreds of high paying jobs.

 

Scroll to top